| Region | District | DBE % | VBP % | Federal Project # |
|---|---|---|---|---|
| 1 | 1 | 11.00 | 0.00 | N/A |
| County(s) | IL Project # | Airport | Sponsor | City |
|---|---|---|---|---|
|
UGN 4631 | Waukegan National | Waukegan Port District | Waukegan |
| Contract Specifics |
|---|
| The time limit to award this item has been changed from 45 days to 60 days after the scheduled letting. |
| 54 Calendar Days |
| Previously advertised on March 09, 2018 (Item 11A). |
| No More Contract Specifics |
| Pay Item # | UOM | Description | Type | Quantity | Unit Price | ||
|---|---|---|---|---|---|---|---|
| AR150510 | L SUM | ENGINEER'S FIELD OFFICE | Base items | 1.000 | |||
| AR150520 | L SUM | MOBILIZATION | Base items | 1.000 | |||
| AR150530 | L SUM | TRAFFIC MAINTENANCE | Base items | 1.000 | |||
| AR152410 | CU YD | UNCLASSIFIED EXCAVATION | Base items | 315.000 | |||
| AR156510 | FOOT | SILT FENCE | Base items | 635.000 | |||
| AR156520 | EACH | INLET PROTECTION | Base items | 3.000 | |||
| AR156531 | SQ YD | EROSION CONTROL BLANKET | Base items | 2,399.000 | |||
| AR156533 | ACRE | TEMPORARY SEED AND MULCH | Base items | 0.400 | |||
| AR201661 | FOOT | CLEAN & SEAL BITUMINOUS CRACKS | Base items | 664.000 | |||
| AR201662 | S.Y. | BITUMINOUS SAND MIX | Base items | 1,486.000 | |||
| AR201663 | FOOT | SAND MIX CRACK REPAIR | Base items | 212.000 | |||
| AR201670 | SQ YD | CRACK CONTROL FABRIC | Base items | 1,621.000 | |||
| AR209607 | SQ YD | CRUSHED AGG. BASE COURSE - 7" | Base items | 589.000 | |||
| AR209609 | S.Y. | CRUSHED AGG. BASE COURSE-9" | Base items | 562.000 | |||
| AR401613 | TON | BIT. SURF. CSE.-METHOD I, SUPERPAVE | Base items | 647.000 | |||
| AR401650 | SQ YD | BITUMINOUS PAVEMENT MILLING | Base items | 6,158.000 | |||
| AR401660 | FOOT | SAW & SEAL BIT. JOINTS | Base items | 366.000 | |||
| AR401665 | FOOT | BITUMINOUS PAVEMENT SAWING | Base items | 3,812.000 | |||
| AR401910 | SQ YD | REMOVE & REPLACE BIT. PAVEMENT | Base items | 13.000 | |||
| AR602510 | GALLON | BITUMINOUS PRIME COAT | Base items | 177.000 | |||
| AR603510 | GALLON | BITUMINOUS TACK COAT | Base items | 924.000 | |||
| AR620535 | SQ FT | PAVEMENT MARKING-THERMOPLASTIC | Base items | 1,093.000 | |||
| AR751411 | EACH | INLET-TYPE A | Base items | 1.000 | |||
| AR800905 | S.Y. | EDGE REPAIR | Base items | 90.000 | |||
| AR800907 | FOOT | INFILTRATION TRENCH | Base items | 100.000 | |||
| AR901510 | ACRE | SEEDING | Base items | 0.600 | |||
| AR905520 | CU YD | TOPSOILING (FROM OFF SITE) | Base items | 218.000 | |||
| AS152410 | CU YD | UNCLASSIFIED EXCAVATION | Additive 1 | 120.000 | |||
| AS156531 | SQ YD | EROSION CONTROL BLANKET | Additive 1 | 3,925.000 | |||
| AS156533 | ACRE | TEMPORARY SEED AND MULCH | Additive 1 | 0.100 | |||
| AS208604 | SQ YD | 4" AGGREGATE BASE COURSE | Additive 1 | 396.000 | |||
| AS501604 | S.F. | 4" PCC SIDEWALK | Additive 1 | 3,557.000 | |||
| AS620535 | S.F. | PAVEMENT MARKING-THERMOPLASTIC | Additive 1 | 310.000 | |||
| AS754904 | FOOT | REMOVE COMB CURB & GUTTER | Additive 1 | 11.000 | |||
| AS754924 | L.F. | REPLACE COMB CURB & GUTTER | Additive 1 | 11.000 | |||
| AS901510 | ACRE | SEEDING | Additive 1 | 0.100 | |||
| AS905520 | C.Y. | TOPSOILING (FROM OFF SITE) | Additive 1 | 52.000 | |||
| AS910200 | EACH | ROADWAY SIGN | Additive 1 | 7.000 | |||
| AS910915 | EACH | REMOVE ROADWAY SIGN | Additive 1 | 1.000 | |||
| AT152410 | CU YD | UNCLASSIFIED EXCAVATION | Additive 2 | 80.000 | |||
| AT156531 | SQ YD | EROSION CONTROL BLANKET | Additive 2 | 2,615.000 | |||
| AT156533 | ACRE | TEMPORARY SEED AND MULCH | Additive 2 | 0.100 | |||
| AT208604 | S.Y. | 4" AGGREGATE BASE COURSE | Additive 2 | 289.000 | |||
| AT501604 | SQ FT | 4" PCC SIDEWALK | Additive 2 | 2,597.000 | |||
| AT620535 | S.F. | PAVEMENT MARKING-THERMOPLASTIC | Additive 2 | 60.000 | |||
| AT901510 | ACRE | SEEDING | Additive 2 | 0.100 | |||
| AT905520 | C.Y. | TOPSOILING (FROM OFF SITE) | Additive 2 | 40.000 | |||
| No More Pay Items | |||||||